Whiteland

Branded-residence luxury on the Southern Peripheral Road.

Private

Truth Verdict

Mostly on schedule, with gaps — 1 of 2 judged behind schedule, delivered ones 6.7 months late on average across Whiteland's 12 filed projects, 2 delivered. The balance sheet reads mixed.

01

About the developer

Whiteland is an active Gurugram developer; we hold in-depth reports on 6 of its projects. The read below is our own — delivery and delay history from public RERA filings, financial health from published financials, not the developer's marketing.

02

Track record

Projects we track

Flagship projects

  • Whiteland Urban Resort / Westin Residences Phase - 2

In the pipeline

  • Whiteland Urban Resort
  • Whiteland Urban Resort Phase-2
  • Whiteland Arena 76
  • Whiteland Urban Resort Phase-3
03

Performance

12

Projects launched

2

Delivered

10

Ongoing

On schedule · locked

Avg delay · locked

Across every Gurugram project we track for this developer — delivered, ongoing and lapsed. Not scoped to one micro-market.

Free · no card

How reliably does Whiteland deliver?

Unlock the on-schedule share and the average slippage across this developer's filed projects — with a number.

or

Buyer-side only — no broker calls, no spam. The project reads stay open to you.

04

Financial health

38/100 · STRAINEDCR: Unrated / Secured NBFC FacilitiesGroup: Whiteland Group (Sardana Family)

Leverage · locked

Interest Coverage · locked

Cash Conversion · locked

Operating Margin · locked

Inventory Cover · locked

Forensic Analyst Audit Note

A directional read on Whiteland's financial health. The full audited financials and the per-project forensics are inside each report — unlock one for the complete numbers.

Verified Source: Ministry of Corporate Affairs (MCA-21) Form AOC-4 Statutory Financial Filing (CIN: U70109HR2021PTC092905)
📄 View Official Audited Statement (PDF) →
05

News & updates

Live12 verified updates

News & Updates

Every verified ground event on Whiteland — filings, construction, JVs, corridor infrastructure and pricing — read for what it means to a buyer.

19 Oct 2026Regulatory

HERC grants 25-year parallel power distribution licence for Gurugram, Nuh to Eleven Power

  • The Haryana Electricity Regulatory Commission (HERC) has granted Eleven Power Private Limited a parallel distribution licence for Gurugram and Nuh revenue districts for 25 years under Section 14 of the Electricity Act, 2003.
Forensic impact read

HERC granted a 25-year parallel power-distribution licence for Gurugram and Nuh to a private company, alongside the existing state discom. Over time this can give residents a second electricity supplier; tariffs, the coverage area and rollout timing are what to watch. Update (23 Oct): after a strike by power employees, the state government assured them there would be no privatisation (ThePrint), so whether this licence is actually rolled out is now uncertain. Talks resume on 3 Nov.

1 Oct 2026Regulatory

CAQM Winter GRAP Stage III/IV Guidelines Enforced: Complete Ban on C&D Activities, Earthwork & RCC Casting Across NCR

  • Commission for Air Quality Management (CAQM) invokes strict Winter Graded Response Action Plan (GRAP Stage III/IV) measures across Delhi-NCR following severe air quality deterioration (AQI >400).
  • Mandates complete cessation of construction and demolition (C&D) activities, including earthwork, excavation, piling, concrete mixing/casting, and transit of loose building materials across Gurugram.
  • Non-earthwork site operations subject to strict anti-smog gun deployment and water-sprinkling mandates.
Forensic impact read

Immediate site halt freezes ongoing structural casting and superstructure progress; introduces potential 30–60 day milestone slippage risks; elevates idle machinery carrying and labor retention costs for developers across active under-construction developments.

Ref CAQM/DIR/GRAP-2026-10Verify filing ↗
22 Sept 2026Regulatory

Gurugram tightens construction and demolition waste rules; no Occupancy Certificate without disposal proof

  • The Municipal Corporation of Gurugram (MCG) has tightened rules for construction and demolition (C&D) waste management, making proof of proper waste disposal a mandatory requirement for obtaining Occupancy Certificates (OCs) and Completion Certificates (CCs).
Forensic impact read

MCG will not issue an Occupancy Certificate without proof of construction-and-demolition waste disposal — a new compliance gate that can delay OC/possession timelines across Gurugram projects.

11 Sept 2026Regulatory

Gurugram waterlogging: HHRC orders city-wide drainage audit, summons GMDA report by December 15

  • The Haryana Human Rights Commission (HHRC) has taken suo motu cognizance of recurring Gurugram waterlogging, calling it a problem that "goes beyond a temporary disruption caused by heavy rainfall" and ordering a comprehensive city-wide civic infrastructure audit.
22 Jul 2026Corporate / JV📌 Landmark

Whiteland Corporation Contracts Shapoorji Pallonji for Turnkey EPC Execution across Sector 76 Assets

  • Whiteland executed ₹1,200 Cr EPC contract with Shapoorji Pallonji Engineering & Construction for Sector 76 developments.
  • Incorporates Mivan aluminium formwork and third-party Bureau Veritas quality monitoring.
Forensic impact read

Tier-1 engineering contractor substantially mitigates project execution and delivery slippage risks.

Ref CW/EPC/WHITELAND-SP-S76Verify filing ↗
8 Jul 2026Corporate / JV📌 Landmark

Marriott International Inks Brand Licensing for India's First Standalone Westin Residences in Sector 103

  • Whiteland and Marriott International signed definitive agreement for branded serviced residences in Sector 103.
  • Includes dedicated concierge, Westin Heavenly Spa, 24/7 in-residence dining, and Marriott Bonvoy elite status.
Forensic impact read

Branded global hospitality premium delivers 30%+ higher rental yield potential over non-branded luxury.

Ref HN/BRANDS/WESTIN-GGM-103Verify filing ↗
24 Jun 2026Corridor Infra

Gurugram’s Southern Peripheral Road Elevated Corridor Project Re-Enters Planning Stage As GMDA Seeks Fresh DPR For Key Stretch

  • Bookmark stories for easy access on any device or the Swarajya app . The Gurugram Metropolitan Development Authority (GMDA) has restarted planning for the long-delayed Southern Peripheral Road (SPR) elevated corridor by inviting bids to prepare a detailed project report (DPR) for the 6 km Ghata Chowk–Vatika Chowk stretch.
swarajyamag.comVerify filing ↗
21 Jun 2026Corridor Infra

Gurugram Railway Station to get direct road link to Dwarka Expressway

  • The Gurugram Railway Station, currently being upgraded under the Centre's Amrit Bharat Station Scheme, is set to get a direct road link to the Dwarka Expressway, with the Gurugram Metropolitan Development Authority (GMDA) preparing to commission a feasibility study to identify the most suitable route.
tribuneindia.comVerify filing ↗
5 Jun 2026Corridor Infra

GMDA withdraws tender for construction of elevated road on SPR

  • The Gurugram Metropolitan Development Authority (GMDA) on Friday withdrew the ₹ 750 crore tender for constructing an elevated road on the Southern Peripheral Road (SPR) from Vatika Chowk to Clover Leaf on the Delhi-Gurugram Expressway, officials said.
hindustantimes.comVerify filing ↗
13 May 2026Corridor Infra

Dwarka Expressway connectivity to get Rs 90 crore road upgrade boost

  • In a major infrastructure push aimed at strengthening connectivity around the Dwarka Expressway corridor, the Gurugram Metropolitan Development Authority (GMDA) has prepared a comprehensive plan worth nearly Rs 90 crore for the repair and redevelopment of around 50 kilometres of roads linked to the expressway.
tribuneindia.comVerify filing ↗
22 Apr 2026Corridor Infra

GMDA plans two flyovers on Dwarka Expressway corridor to ease IMT Manesar traffic

  • In a major push to tackle mounting traffic congestion along the Dwarka Expressway corridor, the Gurugram Metropolitan Development Authority (GMDA) is set to construct two new flyovers, including a key structure at Shaheed Rao Ranjit Singh Chowk in Sector 84. The move is aimed at streamlining traffic flow between Dwarka Expressway and IMT Manesar, a stretch that routinely witnesses heavy vehicular pressure.
tribuneindia.comVerify filing ↗
21 Apr 2026Corridor Infra

Gurugram: 3.5 Km Service Roads Planned, Sector 68–69 Missing Link To Be Completed To Decongest SPR: Report

  • Bookmark stories for easy access on any device or the Swarajya app . With traffic steadily worsening along Gurugram’s Southern Peripheral Road (SPR), the Gurugram Metropolitan Development Authority (GMDA) has initiated plans to strengthen internal connectivity by developing new service roads and completing long-pending road links.
swarajyamag.comVerify filing ↗
News alerts

Get the latest, first.

Verified news on Whiteland, the moment it lands. No spam.

or

12 dispatches· tap the right of a card to advance, the left to go back · colour follows the report’s own rule — green sound, amber watch, rust risk.

06

Frequently asked

Does Whiteland deliver its Gurugram projects on time?

We read this from Whiteland's HARERA filings rather than the brochure — for every tracked Gurugram project, whether it was handed over on or before its RERA-committed possession date, and how far behind the late ones ran. On that record Whiteland is mixed. The exact on-time share and the average slippage sit on this page, free with a mobile number, and no developer pays to change either one.

How many projects has Whiteland delivered in Gurugram?

We track 12 Whiteland projects in Gurugram: 2 delivered, 10 still under construction. Each is scored on delivery, legal standing and pricing in its own report.

Is Whiteland a reliable developer to buy from?

On delivery, Whiteland's tracked record is mixed. But reliability is project-specific: our developer read covers delivery, financial strength and legal signals, and every project Whiteland is building gets its own forensic report and Truth Score. Check the specific project before you book.

See all Whiteland projects