Greater SPR, Gurugram: the ground reality

A 21-km outer ring road from Sector 58 to Manesar has sat in the master plan since 2012. Land compensation for its first stretch was fixed on 13 November 2026. Nothing has been costed, tendered or built yet.

By: Truth Estate Research · reviewed by Gaurav JainPublished: 19 Nov 2026Status checked: 19 Nov 2026
Schematic map: existing SPR and Golf Course Extension Road, and the proposed Greater SPR from Sector 58 to Manesar (indicative alignment, not to scale) NH-48 Dwarka Expressway Sohna Road Faridabad Road SPR Golf Course Extension Road Greater SPR · Phase 1 Greater SPR · Phase 2 Kherki Daula Vatika Chowk Ghata · Sector 58 Badshahpur Manesar Built Greater SPR, indicative Schematic, not to scale
Schematic, not to scale. Greater SPR is drawn from the state budget’s description (“Sector-58 to Manesar”) and the land records’ phasing; no official alignment drawing has been published beyond the 2012 master plan.

“Greater SPR” has become a selling point in Gurugram. It turns up in launch pitches for Golf Course Extension Road, Sector 63A and Badshahpur, usually as a reason today’s price makes sense.

The road is real in one sense. It is a statutory road in Gurugram’s master plan. The state budget named it in March. And on 13 November 2026 the government fixed about ₹986 crore of compensation for land on its first stretch.

In another sense it is not real yet. As of 19 Nov 2026 we found no project cost, no construction tender, no contractor and no official completion date. This piece separates the two, so you can price what exists rather than what has been promised.

Where Greater SPR standsStatus on 19 Nov 2026
In the master planYes, since 2012: a 90-metre road in the Gurugram–Manesar Development Plan 2031
Named in the state budgetYes, 2 March 2026, as “revived”. No construction money allocated
Land, Phase 1 (Faridabad Road to Sohna Road)Compensation announced 13 Nov 2026. Landowners say they will challenge it
Land, Phase 2 (Sohna Road to NH-48, Manesar)Notified. No award. Part of it is in court
Project report, cost, construction approvalNone published
Tender, contractorNone found
ConstructionNot started
Official completion dateNone

What Greater SPR is, and what it is not

It is not the Southern Peripheral Road you can drive on today. That road, the SPR, runs about 12 km from Ghata on the Gurugram–Faridabad Road, through Vatika Chowk on Sohna Road, to NH-48 at Kherki Daula, where it meets the Dwarka Expressway [NBM&CW]. Most people call its Ghata–Vatika stretch Golf Course Extension Road.

Greater SPR is a second, outer road further south. The Haryana Budget 2026–27 describes it as an “approximately 21-km road from Sector-58 to Manesar” that “will function as an outer ring road for New Gurugram” [Budget speech, para 84].

It has legal standing. The Final Development Plan 2031 for Gurugram–Manesar, notified on 15 November 2012, shows a “proposed Greater Southern Peripheral V2(e) road”. Roads of that class reserve 90 metres, with a 30-metre green belt on each side [FDP 2031 notification].

It is planned in two phases:

The two phase lengths add up to 18.7 km, not the budget’s 21 km, and no official source gives a breakdown. Nor has an alignment drawing been published beyond the 2012 plan. Treat any route map in marketing material as indicative. You may also see “Extended SPR”; it is not a name any government document uses.

A road that has been coming since 2013

Acquisition notices were first issued in 2013. Some landowners won a stay from the Punjab and Haryana High Court, the matter went to the Supreme Court, and the stay was vacated in 2025, according to The Tribune [The Tribune].

The name is older than the current route. In 2016 it described a road from Mehrauli to NH-48 at Manesar [NBM&CW, 2016]. In 2018 a “Greater SPR Phase 1” was planned in north Gurugram [NBM&CW, 2018]. Today’s project is the budget’s: Sector 58 to Manesar.

The budget calls it “decade-pending”. Even since its revival, dates have slipped. In December 2025 the state’s urban development authority, HSVP, said Phase 1 acquisition would finish “within the next four to five months” [Daily Jagran]. The award came eleven months later.

The land: where the real progress is

Phase 1 needs 276 acres. About 116 acres have already come in through TDR (transferable development rights): owners, many of them developers who had bought land nearby, gave up road strips in exchange for building rights elsewhere. The other 160 or so acres are being acquired compulsorily.

On Friday 13 November 2026 the Land Acquisition Department announced the award, at HSVP’s request: about ₹986 crore in total [The Tribune].

VillageAward, ₹ crore per acreBase value before uplift, ₹ crore per acre
Badshahpur8.253.68
Maidawas6.172.75
Behrampur5.262.35
Dhumaspur5.192.32
Ullawas4.962.21
Kadarpur4.922.20

Source: The Tribune, 14 Nov 2026. A committee chaired by the HSVP Administrator set the rates.

According to The Tribune, the base value is the average of the costliest 50 of 100 sale deeds registered before 2013, which is then doubled, plus 730 days’ interest. In October the district had asked headquarters for ₹1,012.70 crore to pay Phase 1 compensation [Amar Ujala].

Landowners have rejected the award. Some told The Tribune their land is worth ₹35 crore to ₹100 crore an acre today. Those are their claims, not valuations, but the gap is wide. They say they will go to court, and a mahapanchayat is being planned [Amar Ujala].

Phase 2 is a step behind. Its land is notified but no award has been made. Amar Ujala reports that about 25 acres are NSG (National Security Guard) land, 75 acres fall in a natural conservation zone, and a petition covering a 2 km stretch is pending. We found no public record of the clearances these may need.

What has not happened yet

Construction cannot begin until the land is in hand, a design and cost are approved, money is allocated and a contract is awarded. Phase 1 has only reached the first of those, and that step is now contested.

Don’t confuse it with the SPR projects that are moving

Most buyers on Golf Course Extension Road and the SPR will feel these nearer projects long before Greater SPR:

ProjectStageDetail
SPR elevated road, Vatika Chowk to NH-48 (Package 1, 4.23 km)Tendered₹776 crore excluding GST; bids closed 18 Nov 2026; 30 months from award. An earlier ₹755 crore tender was scrapped in June [Construction World] [Swarajya]
SPR elevated road, Vatika Chowk to Ghata (8.84 km)Budgeted₹1,846 crore; project report in preparation
Golf Course Extension Road, eight-lane upgradeAwardedContractor mobilised in May 2026; physical start not confirmed [The Tribune]
Vatika Chowk underpassOperationalSince November 2023 [The Tribune]
Sohna elevated road (NHAI)OperationalSince 2022
Dwarka Expressway, Haryana sectionOperationalSince 11 Mar 2024 [PIB]
Namo Bharat RRTS, Gurugram–Faridabad–NoidaApproved by the stateFinal alignment approved; ₹15,746 crore (budget, para 57)
Metro, Sector 56 to PachgaonProposedAt project-report stage [Swarajya]

Who it would help, if it is built

This section is Truth Estate’s analysis, not reported fact. It assumes the alignment described in the budget and the land records.

Prices already reflect the roads that exist. Truth Estate tracks 29 live projects on Golf Course Extension Road, with a reference rate of about ₹23,500 per sq ft, and 25 on the SPR at about ₹16,000 (our data, 19 Nov 2026). No data can yet separate a “Greater SPR premium” from the connectivity those sectors already have.

What history says about timing

Gurugram’s big roads have opened years after they were announced, and prices have tended to move when construction became visible and the wider market rose, not on the day of the announcement. Developers’ own delivery records are in our delivery audit.

The risks

What to expect over the next three to five years

These are scenarios, not forecasts, and none of them is a return promise.

Our view

Greater SPR is a legitimate long-term road. It has statutory backing and a real land award, which is more than many announced roads in Gurugram have.

It is not a reason to pay a premium today. Price a home on the roads that exist and the ones under contract: Golf Course Extension Road, the SPR and its elevated corridor, the Sohna elevated road and the Dwarka Expressway. Treat Greater SPR as an upside with no date attached.

If a developer cites it, ask three questions:

  1. Where does the master-plan drawing put the road relative to this project?
  2. Does any access to the project depend on the road being built?
  3. What is the price without it?

We will update this page at each change of stage: a Phase 2 award, a project report, a tender, the start of construction.

Weighing a home on this corridor?

Every project report prices the home on the connectivity that exists, alongside its delivery record, legal standing and fair price per sq ft.

Find your project’s report →

Sources

Official

News and research

Truth Estate is independent and is not paid by developers. Figures are as published by the sources linked; landowners’ and developers’ statements are reported as claims. Status as of 19 Nov 2026. Analysis and scenarios are Truth Estate’s own and are not investment, legal or financial advice. How we work: methodology.