Godrej Aria & 101 Ph 3 — 60s Video Brief

Key Briefing Takeaways (Live Derived)Score: 64/100 (High Risk)
🏗️
Civil Pacing
Tracking 20.9 months behind schedule.
📅
Delivery Forecast
Delivery forecast: 18.1 months after the RERA date.
📊
Financial Health
Financial Health: 75/100 · Truth Estate rating
⚖️
Standardized Rating
Truth Score 64/100 (High Risk). Independent rating.
Verified Public Record · Zero Developer Sponsorship
Transcript

What the Godrej Aria & 101 Ph 3 brief says

Godrej Aria and 101 Phase Three is on the Southern Peripheral Road, starting from one point seven crore.

Here is Truth Estate's sixty-second video brief.

First, civil construction. Civil execution is tracking twenty point nine months behind schedule, forecasting handover around March 2030, eighteen point one months past its August 2028 RERA deadline.

Second, developer financials. Godrej holds a Financial Health rating of seventy-five out of a hundred, a Truth Estate rating.

Third, footprint and density. Fifty-two point two apartments per acre across two point eight-four acres, with eighty-eight percent open area.

Our standardized Truth Score: sixty-four out of a hundred. High Risk.

Data as of 30 Oct 2026.

Explore the full report at truthestate.in.

Recorded with data as of 30 Oct 2026. The full report carries the latest figures.