Eldeco Terra & Sol — 60s Video Brief

Key Briefing Takeaways (Live Derived)Score: 65/100 (Watchlist)
🏗️
Civil Pacing
Tracking 5.8 months behind schedule.
📅
Delivery Forecast
Delivery forecast: 4.8 months after the RERA date.
📊
Financial Health
Financial Health: 85/100 · Truth Estate rating
⚖️
Standardized Rating
Truth Score 65/100 (Watchlist). Independent rating.
Verified Public Record · Zero Developer Sponsorship
Transcript

What the Eldeco Terra & Sol brief says

Eldeco Terra and Sol is in Sector 80 in New Gurgaon, starting from two point eight crore.

Here is Truth Estate's sixty-second video brief.

First, civil construction.

Civil execution is tracking five point eight months behind schedule, projecting handover around June 2031, four point eight months past its January 2031 RERA date.

Second, developer financials.

Eldeco carries a Financial Health rating of eighty-five out of a hundred, a Truth Estate rating.

Third, legal standing.

Legal Health is ninety out of a hundred, a Truth Estate rating.

Fourth, planning and density.

Eighty-three apartments per acre across two point seven acres, with seventy-nine point three percent open area.

Our standardized Truth Score: sixty-five out of a hundred.

Watchlist.

Data as of 2 Nov 2026.